Infrastructure project for satisfying water demand

“The construction of the underground pumping station Gorica and its connection to the island Pag water supply system” is another infrastructure project for which CER offered consulting services based on its wide expertise in the public infrastructure sector.

The 1.408.800,00 kuna worth project will be significant for local residents since it will secure the necessary drinking water in the summer months when there is a higher demand for drinking water. The higher water supply will be possible given the technical characteristics of the new pumping station which are as follows:

Number of stations: 3

Maximum water flow: 70,83 l/s

Nominal pump head: 47,22 m

CER, in partnership with another engineering company, prepared the whole project proposal.